Before Construction

Excavation

Plumbing

Steel

Shotcrete

Boulders / Rock Waterfall

Flagstone

Deck Framing

Deck Concrete

Equipment Wall

Acrylic Decking
Palm Trees
Stucco
& Paint
Landscape Lighting
Pebble Tec Finish

Landscaping Rocks

Completed

|
|






View the construction from 4 angles

| |
• Raised Spa with
Rock Waterfall
• Pebble Tec Interior
• 8' Deep End
• In-Floor Cleaning System
• Automated Wireless Controls
• SAM / SAL Color Lighting
• Acrylic Deck & Flagstone Coping
• Gas Heater (400kBTU)
•
Genuine Rock Boulders
• 90' Perimeter, 19800 gal
Detailed Specifications |
Pool
built by:
We believe the company that did our pool
and spa is the best in the Phoenix Valley. If you live
in the area and are considering a pool, Contact
Us and we will be happy to answer any questions,
and tell you how you can end up with a better pool while spending less
money.
Masonry/Stucco: Brad Symolon
Painting: Steve Rockwell (The Masters)
Palm Trees: Moon Valley
Landscaping, Irrigation, Lighting & Sound: Owner

| |
Done by Pool Company:
Layout: Feb. 21
Excavation: Feb. 23-24
Plumbing: Feb. 27-28, Mar. 7-8
Steel: Mar. 3-4, 6
Electrical: Mar. 7
Shotcrete: Mar. 13
Gas Line: Mar. 14
Boulders / Rock Waterfall: Mar. 17
Flagstone: Mar. 21-22
Deck Form/Concrete: Mar. 27-28
Deck Acrylic: Apr. 4-6
Cleanup: Apr. 10
Pebble Tec Surfacing: Apr. 19-20
Filled: Apr. 21
Final Startup: Apr. 22
Non-Pool Items:
Equipment Wall: Mar. 30-31
Outer Wall Repair, Stucco: Apr. 3-7
Palm Trees Planted: Apr. 11
Irrigation System: Apr. 12-16
Outdoor "Rock" Speakers: Apr. 12
Landscape Lighting: Apr. 14-17
Painting of Walls: Apr. 15
Landscaping Rocks (54 Tons): Apr. 19-20 |
|